HDOT-A Diamondhead Concourse Gate 6 Modernization
Honolulu HI
On-Site design team leader and Project Manager responsible for all aspects of project delivery, client interaction and multidisciplinary team coordination. The 34,000 SF2 four gate concourse expansion included new public restrooms, escalators, elevators, concessions and seating for over 500 passengers. In addition to Terminal expansion, the design build effort under Hensel Phelps, also included various airfield landside and airside improvements including hardstand restriping, egress stair, waste triturator and protected walkway.
Project Cost: $65 Million
Project Dates: March 2017 to March 2019
Completed while employed as Project Manager with Landrum & Brown